DOT OIG recommendation AV2018030-2
Develop and implement a quality control checklist with criteria for determining when the use of incremental funding prior to PLA approval is…
The recommendation, in the publisher's words
Develop and implement a quality control checklist with criteria for determining when the use of incremental funding prior to PLA approval is permissible.
- Responsible agency
- Federal Aviation Administration
- Issued
- March 6, 2018
- Report
- FAA Needs To Strengthen Its Management Controls Over the Use and Oversight of NextGen Developmental Funding (AV2018030) · find it at DOT OIG
- Closed
- March 30, 2023 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
5 more, of which 0 are open in the publisher's file.
- Define the projects that are considered pre-implementation (developmental) in the Agency budget guidance and Acquisition Management System policy and validate that developmental projects…DOT OIG AV2018030-1 · issued Mar 6, 2018 · closed Sep 29, 2021Closed
- Develop and implement a control for enforcing the PMA limits on the assessment of program management fees for various administrative and contract support specified in the Agency's standard…DOT OIG AV2018030-3 · issued Mar 6, 2018 · closed Mar 30, 2023Closed
- Update PMA standard operating procedures to include a control that ensures project requirements are met before transferring expiring funds into the PMA account.DOT OIG AV2018030-4 · issued Mar 6, 2018 · closed Oct 24, 2018Closed
- Amend the PLA close-out process to include the statement of outcomes and statement that work was concluded or if follow-on work is required.DOT OIG AV2018030-5 · issued Mar 6, 2018 · closed Aug 21, 2018Closed
- Establish and implement a mechanism for providing oversight of developmental funding, to include records of decision regarding selecting, justifying, and measuring the outcomes of PLAs to…DOT OIG AV2018030-6 · issued Mar 6, 2018 · closed Mar 30, 2023Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.