DOT OIG recommendation AV2025044-6
Establish a process to provide reasonable assurance that project managers comply with FAA's Airport Improvement Program, grant oversight, and grant…
The recommendation, in the publisher's words
Establish a process to provide reasonable assurance that project managers comply with FAA's Airport Improvement Program, grant oversight, and grant payment policies for the assessment of airport sponsors' risks and approval of sponsors' grant payment requests.
- Responsible agency
- Federal Aviation Administration
- Issued
- September 17, 2025
- Report
- FAA’s Oversight of Infrastructure Investment and Jobs Act Funds is Hindered by Unclear Policies and Internal Control Challenges (AV2025044) · find it at DOT OIG
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
5 more, of which 5 are open in the publisher's file.
- Clarify for project managers the types of changes to an airport sponsor's condition that would trigger the need for a project manager to conduct an interim risk assessment of the sponsor's…DOT OIG AV2025044-1 · issued Sep 17, 2025Open
- Clarify the grant payment policy on how a project manager should use the Project Manager Assessment Checklist to determine an airport sponsor's grant payment risk level and how project…DOT OIG AV2025044-2 · issued Sep 17, 2025Open
- Determine whether the $338 million questioned in this report as unsupported costs are supported and allowable.DOT OIG AV2025044-3 · issued Sep 17, 2025Open
- Recover any of the $338 million questioned in this report as unsupported costs that are determined to be unsupported or unallowable.DOT OIG AV2025044-4 · issued Sep 17, 2025Open
- Provide formal training to project managers on how to conduct risk assessments, determine risk levels, and conduct oversight in accordance with FAA's Airport Improvement Program, grant…DOT OIG AV2025044-5 · issued Sep 17, 2025Open
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.