AuditLine › DOT OIG › Pipeline and Hazardous Materials Safety Administration
DOT OIG recommendation FI2016024-9
Conduct annual functional contingency plan testing for the PHMSA Hazardous Materials Information System.
The recommendation, in the publisher's words
Conduct annual functional contingency plan testing for the PHMSA Hazardous Materials Information System.
- Responsible agency
- Pipeline and Hazardous Materials Safety Administration
- Issued
- March 3, 2016
- Report
- Multiple DOT Operating Administrations Lack Effective Information System Disaster Recovery Plans and Exercises (FI2016024) · find it at DOT OIG
- Closed
- January 30, 2017 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
8 more, of which 0 are open in the publisher's file.
- Develop, document, and implement user and system-level data backup processes for the FMCSA Enforcement Management Information System.DOT OIG FI2016024-1 · issued Mar 3, 2016 · closed Apr 13, 2017Closed
- Develop, document, and implement user and system-level data backup processes for the FRA Railroad Safety Information System.DOT OIG FI2016024-2 · issued Mar 3, 2016 · closed Jan 30, 2017Closed
- Specify alternate telecommunications services including necessary agreements for the FMCSA Enforcement Management Information System contingency plan.DOT OIG FI2016024-3 · issued Mar 3, 2016 · closed Aug 25, 2020Closed
- Specify alternate telecommunications services including necessary agreements for the PHMSA Hazardous Materials Information System contingency plan.DOT OIG FI2016024-4 · issued Mar 3, 2016 · closed Sep 13, 2017Closed
- Update the contingency plans for the two FHWA systems: (1) Fiscal Management Information System and (2) Rapid Approval and State Payment System (RASPS) by: a. Developing a Business Impact…DOT OIG FI2016024-5 · issued Mar 3, 2016 · closed Jan 30, 2017Closed
- Conduct annual functional contingency plan testing for FAA systems, including (1) Enhanced Flight Standards Automation System and (2) Web-based Operations Safety System.DOT OIG FI2016024-6 · issued Mar 3, 2016 · closed Nov 21, 2016Closed
- Conduct annual functional contingency plan testing for the FRA Railroad Safety Information System.DOT OIG FI2016024-7 · issued Mar 3, 2016 · closed Jan 30, 2017Closed
- Conduct annual functional contingency plan testing for the FMCSA Enforcement Management Information System.DOT OIG FI2016024-8 · issued Mar 3, 2016 · closed Sep 14, 2017Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.