DOT OIG recommendation QC2024015-5
KPMG recommends that FAA update its procurement policy to define the period of time permitted to document a contractor's oral agreement.
The recommendation, in the publisher's words
KPMG recommends that FAA update its procurement policy to define the period of time permitted to document a contractor's oral agreement.
- Responsible agency
- Federal Aviation Administration
- Issued
- January 31, 2024
- Report
- Quality Control Review of the Management Letter for the Federal Aviation Administration’s Audited Consolidated Financial Statements for Fiscal Years 2023 and 2022 (QC2024015) · find it at DOT OIG
- Closed
- July 28, 2026 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
7 more, of which 1 is open in the publisher's file.
- KPMG recommends that FAA management require privileged users on the Windows virtual machine environment to authenticate using MFA. If it is not technically feasible, then we recommend that…DOT OIG QC2024015-1 · issued Jan 31, 2024 · closed Jun 30, 2026Closed
- KPMG recommends that FAA management design and implement documented control activities to monitor the effective operation of its existing process controls related to: Provisioning of new…DOT OIG QC2024015-2 · issued Jan 31, 2024 · closed Sep 11, 2026Closed
- KPMG recommends that FAA management take measures to ensure that FAA has sufficient control operator personnel available to support the annual recertification of FAA employees with system…DOT OIG QC2024015-3 · issued Jan 31, 2024 · closed Sep 11, 2026Closed
- KPMG recommends that FAA design and implement a procedure to identify and timely record contracting actions within the general ledger that were executed outside of the standard business…DOT OIG QC2024015-4 · issued Jan 31, 2024 · closed Jul 28, 2026Closed
- KPMG recommends that FAA reinforce existing controls, to review individual lease payment schedules upon lease commencement or modification to ensure that the schedules are consistent with…DOT OIG QC2024015-6 · issued Jan 31, 2024 · closed Apr 17, 2026Closed
- KPMG recommends that FAA design and implement procedures within its existing PP&E Accrual to obtain a complete listing of trailing costs related to completed assets and accrue for such…DOT OIG QC2024015-7 · issued Jan 31, 2024 · closed Jul 28, 2026Closed
- KPMG recommends that management design and implement procedures to verify the completeness and accuracy of the non-LOI accrual average billing cycle data input used in the estimate…DOT OIG QC2024015-8 · issued Jan 31, 2024Open
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.