DOT OIG recommendation ZA2012082-2

That FAA's Vice President of Business and Acquisition Services: Revise AMS to require that, when IGCEs exceed contractor proposals by 15 percent or…

ClosedThe publisher's status, as reported by DOT Office of Inspector General in the file read .

The recommendation, in the publisher's words

That FAA's Vice President of Business and Acquisition Services: Revise AMS to require that, when IGCEs exceed contractor proposals by 15 percent or more, program officials submit an explanation and recommended corrective actions to the CFO before contract award.
Responsible agency
Federal Aviation Administration
Issued
March 28, 2012
Report
FAA's Contracting Practices are Insufficient to Effectively Manage its Systems Engineering 2020 Contracts (ZA2012082) · find it at DOT OIG
Closed
July 12, 2016 (publisher's date)

“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.

Dated history

  1. Issued by DOT OIG. (publisher's date)
  2. Closed, with status “Closed”. (publisher's date)
  3. First recorded by AuditLine. (start of AuditLine's own history for this record)

Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.

Other recommendations from this report

11 more, of which 0 are open in the publisher's file.

Source

Open this report in DOT OIG's tracker This publisher's records (CSV)

Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows, SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.