DOT OIG recommendation ZA2015003-1
Implement a detailed process for OSPE staff to regularly evaluate Operating Administrations' compliance with departmental and Federal timeframes for…
The recommendation, in the publisher's words
Implement a detailed process for OSPE staff to regularly evaluate Operating Administrations' compliance with departmental and Federal timeframes for (a) initiating an S&D action (within the DOT S&D Order 45-day requirement) and (B)reporting to SAM (3 days for procurement actions; 5 days for non-procurement actions). This process should include follow-up actions to correct instances of noncompliance.
- Responsible agency
- Office of the Secretary of Transportation
- Issued
- October 15, 2014
- Report
- DOT’s Suspension and Debarment Program Continues To Have Insufficient Controls (ZA2015003) · find it at DOT OIG
- Closed
- February 11, 2016 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
6 more, of which 0 are open in the publisher's file.
- Require all Operating Administrations to establish or update their S&D procedures to implement Federal S&D requirements and the DOT S&D Order, including a) requiring recipients to report…DOT OIG ZA2015003-2 · issued Oct 15, 2014 · closed Jun 28, 2017Closed
- Implement detailed procedures for regularly verifying the accuracy and completeness of the data reported to the DOT S&D systemincluding, at a minimum, the key data fields needed for OSPE…DOT OIG ZA2015003-3 · issued Oct 15, 2014 · closed Apr 18, 2016Closed
- Develop a data dictionary for the DOT S&D system that defines each data field and identifies which fields to populate. Make this data dictionary available to all relevant stakeholders and…DOT OIG ZA2015003-4 · issued Oct 15, 2014 · closed Jun 23, 2016Closed
- Revise the DOT S&D Order to reflect the transition to SAMincluding revised Federal timeframes for entering data into SAM.DOT OIG ZA2015003-5 · issued Oct 15, 2014 · closed Mar 23, 2016Closed
- Implement a detailed process for OSPE staff to regularly reconcile data in the DOT S&D system and SAMincluding steps for identifying and correcting data discrepancies. Using this new…DOT OIG ZA2015003-6 · issued Oct 15, 2014 · closed Apr 18, 2016Closed
- Conduct and document quarterly internal S&D meetings with all Operating Administrations and S&D stakeholders, as established in the DOT S&D Order.DOT OIG ZA2015003-7 · issued Oct 15, 2014 · closed Mar 23, 2016Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.