DOT OIG recommendation ZA2020020-8
Strengthen internal controls to verify compliance with Agency requirements regarding completion and approval of source selection evaluation plans…
The recommendation, in the publisher's words
Strengthen internal controls to verify compliance with Agency requirements regarding completion and approval of source selection evaluation plans for major program contracts.
- Responsible agency
- Federal Aviation Administration
- Issued
- March 9, 2020
- Report
- FAA’s Competitive Award Practices Expose Its Major Program Contracts to Cost and Performance Risks (ZA2020020) · find it at DOT OIG
- Closed
- July 6, 2022 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
9 more, of which 0 are open in the publisher's file.
- Revise the Acquisition Management System (AMS) and/or FAA’s Contract Pricing Handbook to address challenges around conducting appropriate price and cost analyses in order to reliably…DOT OIG ZA2020020-1 · issued Mar 9, 2020 · closed May 10, 2021Closed
- Strengthen internal controls to verify compliance with Agency requirements for maintaining centralized files for major program contractsâ"including a complete record of the acquisition…DOT OIG ZA2020020-10 · issued Mar 9, 2020 · closed Jul 6, 2022Closed
- Revise AMS to require acquisition planning for both competitive and noncompetitive major program contracts to allow adequate time and the possibility for achieving competition of option…DOT OIG ZA2020020-2 · issued Mar 9, 2020 · closed May 7, 2021Closed
- Strengthen internal controls to verify that all independent government cost estimates (IGCE) are completed in compliance with Agency requirements prior to the award of a major program…DOT OIG ZA2020020-3 · issued Mar 9, 2020 · closed Jul 6, 2022Closed
- Revise AMS to clarify requirements around what actions the Program Office must take prior to the award of a major program contract when an IGCE varies by more than 15 percent from the…DOT OIG ZA2020020-4 · issued Mar 9, 2020 · closed Mar 8, 2021Closed
- Strengthen internal controls to hold acquisition and program officials accountable for providing timely signatures on packages for any major program contract procurement actionâ"such as…DOT OIG ZA2020020-5 · issued Mar 9, 2020 · closed Jan 5, 2023Closed
- Strengthen internal controls to ensure a sound rationale is documented to support each noncompetitive major program contract, per Agency requirements, before the award is made.…DOT OIG ZA2020020-6 · issued Mar 9, 2020 · closed Jul 6, 2022Closed
- Strengthen internal controls to verify compliance with Agency requirements for conflict of interest agreements to be completed by all officials involved in a major program contract source…DOT OIG ZA2020020-7 · issued Mar 9, 2020 · closed Jul 6, 2022Closed
- Strengthen internal controls to verify compliance with Agency requirements to use code names in lieu of contractor names in all source selection and evaluation communication and…DOT OIG ZA2020020-9 · issued Mar 9, 2020 · closed Jul 6, 2022Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.