AuditLine › DOT OIG › Federal Aviation Administration
DOT OIG recommendation ZA2024019-2
Implement a written process for verifying compliance with Agency requirements for developing independent Government cost estimates (IGCEs) for…
The recommendation, in the publisher's words
Implement a written process for verifying compliance with Agency requirements for developing independent Government cost estimates (IGCEs) for contract modifications. Implementing this recommendation could put up to $311.6 million in Federal funds to better use by improving FAA's ability to establish contract pricing that is fair, reasonable, and realistic.
- Responsible agency
- Federal Aviation Administration
- Issued
- February 26, 2024
- Report
- FAA’s Information Technology and Telecommunications Contracting Practices Limit Best Value Outcomes (ZA2024019) · find it at DOT OIG
- Closed
- August 29, 2024 (publisher's date)
- Funds put to better use
- $311,611,640 (the publisher's figure; not realised savings)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
6 more, of which 0 are open in the publisher's file.
- Implement a written process for verifying compliance with Agency requirements for maintaining electronic, centralized files that include all documented contractual actions and…DOT OIG ZA2024019-1 · issued Feb 26, 2024 · closed Oct 1, 2024Closed
- Implement a written process for verifying that any extension of a contract's performance period—including exercising an option period—is awarded prior to the contract expiring.DOT OIG ZA2024019-3 · issued Feb 26, 2024 · closed Dec 23, 2024Closed
- Update the Acquisition Management System (AMS) to specify what program offices are required to provide as part of an IT and telecom procurement request package. This documentation should…DOT OIG ZA2024019-4 · issued Feb 26, 2024 · closed Jun 18, 2025Closed
- Update AMS to include limitations on how long contracts can be extended.DOT OIG ZA2024019-5 · issued Feb 26, 2024 · closed Sep 26, 2025Closed
- Implement written guidance to explain what authorities are appropriate to use to extend contracts beyond their initial performance periods, including any limitations associated with using…DOT OIG ZA2024019-6 · issued Feb 26, 2024 · closed May 15, 2025Closed
- Update AMS to include when it is allowable and what is required to add work outside of a contract's scope after the award is made.DOT OIG ZA2024019-7 · issued Feb 26, 2024 · closed Aug 5, 2024Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.