DOT OIG recommendations · Department of Transportation
Federal Transit Administration
25 open and 342 closed recommendations from DOT Office of Inspector General name this office as responsible, in the publisher's own file.
Source: DOT OIG Recommendation Dashboard, official export read .
25openpublisher's status
342closedall closed statuses
12open five years or morecounted from the issue date
Jun 6, 2017oldest open, issued
| Publisher's status | Recommendations |
|---|---|
| Closed | 342 |
| Open | 25 |
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Open recommendations, oldest first
- Recovers $147,515 from the City, if applicable.DOT OIG SA2017052-2 · issued Jun 6, 2017Open
- Recovers $438,118 from the State, if applicable.DOT OIG SA2017076-4 · issued Sep 11, 2017Open
- Ensures that the Authority complies with equipment and real property management requirements.DOT OIG SA2017082-1 · issued Sep 11, 2017Open
- We recommend FTA recovers $76,572 from the Authority, if applicable.DOT OIG SA2018035-3 · issued Mar 19, 2018Open
- We recommend FTA recovers $99,226 from the State, if applicable.DOT OIG SA2018073-2 · issued Aug 22, 2018Open
- We recommend FTA recovers $30,641 from the Authority, if applicable.DOT OIG SA2018078-2 · issued Sep 10, 2018Open
- Recovers $24,080,771 from the City and County, if applicable.DOT OIG SA2018080-2 · issued Sep 10, 2018Open
- Ensures that the Authority complies with the equipment and real property management requirements.DOT OIG SA2019078-1 · issued Sep 17, 2019Open
- Ensures the State complies with the allowable costs/cost principles and subrecipient monitoring requirements.DOT OIG SA2019080-1 · issued Sep 18, 2019Open
- Recovers $232,750 (2018-067) from the State, if applicable.DOT OIG SA2019080-2 · issued Sep 18, 2019Open
- Recovers $71,167 (2018-068) from the State, if applicable.DOT OIG SA2019080-3 · issued Sep 18, 2019Open
- Sensitive information redactedDOT OIG IT2022005-13 · issued Oct 20, 2021Open
- Develop and implement a process to identify and provide oversight of real property to active recipients with new grants that do not receive a triennial or State management review.DOT OIG FS2024025-2 · issued May 20, 2024Open
- Establish and implement a process to verify that FTA’s financial interest in real property dispositions is managed in accordance with FTA Circular 5010.1E. Implementing this recommendation…DOT OIG FS2024025-8 · issued May 20, 2024Open
- For FTA funds identified at elevated risk for misuse, implement written procedures to strengthen the Agency's ability to assess expense eligibility prior to recipients receiving payments.…DOT OIG ZA2024026-4 · issued May 21, 2024Open
- Initiate actions to establish requirements for recipients (or third-party auditors) for how manufacturers' rolling stock documentation will be reviewed when conducting pre-award and…DOT OIG ZA2024033-1 · issued Jul 31, 2024Open
- Initiate actions to establish requirements for recipients (or third-party auditors) to maintain pre-award and post-delivery audit documentation in a manner that protects manufacturers'…DOT OIG ZA2024033-2 · issued Jul 31, 2024Open
- Initiate actions to establish requirements for recipients (or their auditors) to document their verification of suppliers' Buy America information.DOT OIG ZA2024033-4 · issued Jul 31, 2024Open
- Develop and implement Buy America policies or guidance as to how to account for hardware and domestic shipping costs when computing domestic content percentages.DOT OIG ZA2024033-5 · issued Jul 31, 2024Open
- OIG recommends that OST work with the Federal Transit Administration to determine the allowability of questioned tribal transactions and recover $136,402, if applicable.DOT OIG SA2025024-4 · issued Feb 19, 2025Open
- Develop and implement quality control procedures to address identified oversight gaps. The procedures should include a process to ensure findings specify suitable criteria, minimum…DOT OIG ST2025039-2 · issued Aug 13, 2025Open
- FTA communicate the finalized SOP to preparers of the grant accrual workbook to ensure appropriate understanding of the enhanced methodology and review requirements.DOT OIG QC2026019-10 · issued Feb 25, 2026Open
- FTA management implement a quarterly access review process over all integrated Appian platform access reviews in accordance with the DOT Compendium.DOT OIG QC2026019-6 · issued Feb 25, 2026Open
- FTA enhance and finalize the FTA Grant Accrual Standard Operating Procedure (SOP) to more clearly outline the historical day calculation methodology used in the accrual calculation.DOT OIG QC2026019-8 · issued Feb 25, 2026Open
- FTA ensure the review process is sufficient to identify any deviations from the outlined policy.DOT OIG QC2026019-9 · issued Feb 25, 2026Open
Closed recommendations, most recently closed first
- Develop and document implementation of a methodology to verify that CIG applicants that are subject to the TAM performance target progress requirement have made progress on established TAM…DOT OIG ST2026005-1 · issued Dec 17, 2025 · closed Oct 28, 2026Closed
- Develop and implement a plan for how OTrak will accommodate future changes to the SSO audit structure, such as those anticipated as a result of the implementation of risk-based inspections.DOT OIG ST2025039-3 · issued Aug 13, 2025 · closed Aug 26, 2026Closed
- Establish and implement supervisory review of OTrak data entries to identify un- or mis-recorded entries and improve the reliability of OTrak data.DOT OIG ST2025039-4 · issued Aug 13, 2025 · closed Aug 26, 2026Closed
- Develop and provide to State Safety Oversight (SSO) program audit participants a methodology—the steps the FTA Audit Team will take and the indicators the audit team will look at to…DOT OIG ST2025039-1 · issued Aug 13, 2025 · closed Aug 5, 2026Closed
- Develop and implement enhanced monitoring mechanisms for all recipients with unexpended Hurricane Sandy funds that focus on identifying and addressing challenges and delays in managing the…DOT OIG FI2026001-1 · issued Nov 19, 2025 · closed Jul 7, 2026Closed
- Review and take corrective action to address the approximately $95.4 million in questioned costs based on recipients incurring new project costs during lapses in the grants’ periods of…DOT OIG FI2026001-2 · issued Nov 19, 2025 · closed Jul 7, 2026Closed
- Update FTA guidance on conducting timely grant closeout, including potential delays in completing the steps recipients must take between project activity completion and beginning the grant…DOT OIG FI2026001-4 · issued Nov 19, 2025 · closed Jun 1, 2026Closed
- Develop and implement a standardized process to prevent grants' periods of performance from ending before project activities are completed. This should include required timeframes for…DOT OIG FI2026001-3 · issued Nov 19, 2025 · closed May 29, 2026Closed
- Update FTA’s Contractors Manual to require contractors to request a current and complete real property inventory that complies with FTA Circular 5010.1E reporting requirements and require…DOT OIG FS2024025-3 · issued May 20, 2024 · closed May 12, 2026Closed
- Implement a written policy requiring that FTA officials develop and implement enhanced oversight processes to specifically mitigate identified risks associated with any funding…DOT OIG ZA2024026-3 · issued May 21, 2024 · closed Mar 2, 2026Closed
- Update OTrak to enable the complete text of findings and recommendations to be captured in database fields.DOT OIG ST2025039-5 · issued Aug 13, 2025 · closed Feb 24, 2026Closed
- Implement written procedures to test recipients' CARES Act payments using methodologies to sufficiently validate that costs are supported and eligible. These procedures should include…DOT OIG ZA2024026-1 · issued May 21, 2024 · closed Jan 29, 2026Closed
- Implement written procedures to test recipients' financial system controls to prevent duplicate payments from Federal, State, and local sources.DOT OIG ZA2024026-2 · issued May 21, 2024 · closed Jan 29, 2026Closed
- Develop and implement a process to require grant recipients to annually certify, when applicable, adherence to FTA’s requirements for the approval of disposed real property funded with…DOT OIG FS2024025-7 · issued May 20, 2024 · closed Dec 11, 2025Closed
- Develop and implement procedures within FTA's Triennial and State Management Reviews to assess the necessary data to affirm that each grantee undergoing a comprehensive review carries…DOT OIG ST2020005-3 · issued Oct 30, 2019 · closed Sep 30, 2025Closed
- Design or redesign control activities for the four risks that have not been fully addressed and that FTA still deems as applicable. These are: a. Risk of Fraud or Abuse, b. Recipients May…DOT OIG ST2023001-1 · issued Oct 12, 2022 · closed Sep 30, 2025Closed
- Develop and implement Buy America policies or guidance detailing when to initiate Buy America rolling stock compliance reviews and apply the corrective actions (i.e., specific conditions…DOT OIG ZA2024033-6 · issued Jul 31, 2024 · closed Aug 26, 2025Closed
- Develop and implement processes to identify grant awards since FTA's implementation of the Transit Award Management System that provide Federal funding for reportable real property and use…DOT OIG FS2024025-1 · issued May 20, 2024 · closed Jun 30, 2025Closed
- Implement procedures and related mechanisms to show when unobligated transferred funds are obligated and to what projects.DOT OIG ZA2023014-14 · issued Feb 1, 2023 · closed Jun 26, 2025Closed
- Recover the $9,946,977 in costs we identified for which SDOT provided incomplete information or provide a justification for accepting the costs.DOT OIG ZA2023014-11 · issued Feb 1, 2023 · closed Feb 27, 2025Closed
- Include a sample of SDOT's change orders as part of FTA's triennial reviews. In doing so, FTA could better detect and prevent the risk for paying for unapproved change orders.DOT OIG ZA2023014-9 · issued Feb 1, 2023 · closed Feb 27, 2025Closed
- For the $30.8 million in questioned costs relating to CRRC MA suppliers' certificates, work with SEPTA to confirm Buy America compliance for those suppliers and determine if any amount is…DOT OIG ZA2024033-7 · issued Jul 31, 2024 · closed Feb 27, 2025Closed
- Complete FTA's enhanced Buy America review and take correction actions as deemed necessary to address any instances of noncompliance with Buy America rolling stock requirements on the CRRC…DOT OIG ZA2024033-8 · issued Jul 31, 2024 · closed Feb 27, 2025Closed
- Require FTA Region 10 to conduct a review of the City of Seattle's internal controls for supporting documentation of expenditures billed to Federal awards to ensure compliance with 2 CFR…DOT OIG ZA2023014-10 · issued Feb 1, 2023 · closed Jan 15, 2025Closed
- Update FTA Circular 5010.1E to increase clarity for grant recipients regarding FTA's requirements for real property reporting, including the requirement to track all FTA-funded…DOT OIG FS2024025-5 · issued May 20, 2024 · closed Nov 14, 2024Closed
- Update FTA Circular 5010.1E to increase clarity for grant recipients regarding FTA's requirements for real property reporting, including a requirement to report on all real property to…DOT OIG FS2024025-4 · issued May 20, 2024 · closed Nov 7, 2024Closed
- Update FTA Circular 5010.1E to require that grant recipients submit a complete real property inventory in accordance with 2 Code of Federal Regulations § 200.330.DOT OIG FS2024025-6 · issued May 20, 2024 · closed Nov 7, 2024Closed
- KPMG recommends that FTA management evaluate the COVID-19 grant programs and develop an estimation methodology responsive to the nature of the program and expected drawdown patterns.DOT OIG QC2024007-1 · issued Nov 15, 2023 · closed Sep 30, 2024Closed
- Establish and implement written policies and procedures to accurately communicate allocated amounts over time through FTA's documents, such as notices, memoranda, and letters; the grant…DOT OIG ST2021032-1 · issued Jul 21, 2021 · closed Sep 30, 2024Closed
- Recovers $9,377 from the University, if applicable.DOT OIG SA2018087-4 · issued Sep 11, 2018 · closed Sep 26, 2024Closed
- Amend FTA's Master Agreement to clarify that recipients must obtain the same level of access as third-party auditors would have to confidential information to improve oversight and…DOT OIG ZA2024033-3 · issued Jul 31, 2024 · closed Aug 30, 2024Closed
- Ensures that the Authority complies with equipment and real property management requirements.DOT OIG SA2017081-2 · issued Sep 11, 2017 · closed May 23, 2024Closed
- Ensures that the Authority complies with the equipment and real property management requirements.DOT OIG SA2018082-1 · issued Sep 10, 2018 · closed May 23, 2024Closed
- Ensures that the Authority complies with the equipment and real property management requirements.DOT OIG SA2019028-1 · issued Mar 25, 2019 · closed May 23, 2024Closed
- Sensitive information redactedDOT OIG IT2022005-5 · issued Oct 20, 2021 · closed Apr 11, 2024Closed
- KPMG recommends that FTA management design and implement controls to track the status of Treasury warrant requests to ensure that the warrants are recorded in the financial system timely…DOT OIG QC2023016-11 · issued Feb 8, 2023 · closed Dec 13, 2023Closed
- KPMG recommends that FTA management perform a review for the completeness of the financial statements provided to OST, including reviews for transactions recorded subsequent to the OST…DOT OIG QC2023016-12 · issued Feb 8, 2023 · closed Dec 13, 2023Closed
- Require FTA Region 10 to review $3.8 million in inactive funds identified in this report and determine whether they will be used, and if not, deobligated. Implementing this recommendation…DOT OIG ZA2023014-13 · issued Feb 1, 2023 · closed Sep 29, 2023Closed
- Recovers $171,265 from the County, if applicable.DOT OIG SA2017071-2 · issued Aug 9, 2017 · closed Jul 18, 2023Closed
- Direct FTA Region 10 to notify WSDOT in writing that the $3.6 million in lapsed funds identified in this report have been credited to the State and are available for other eligible transit…DOT OIG ZA2023014-12 · issued Feb 1, 2023 · closed Jul 14, 2023Closed
- Document the determination that four of the risk areas in the August 2021 Internal Control Plan are no longer risks; therefore, additional controls are not necessary. These are: a.…DOT OIG ST2023001-2 · issued Oct 12, 2022 · closed May 11, 2023Closed
- Ensures that the County complies with Allowable Costs/Costs Principles requirements.DOT OIG SA2017071-1 · issued Aug 9, 2017 · closed Mar 31, 2023Closed
- Ensures that the State complies with subrecipient monitoring requirements.DOT OIG SA2017076-3 · issued Sep 11, 2017 · closed Mar 31, 2023Closed
- Ensures that the State complies with the subrecipient monitoring requirements.DOT OIG SA2018073-1 · issued Aug 22, 2018 · closed Mar 31, 2023Closed
- Ensures that the Authority complies with the equipment and real property management requirements.DOT OIG SA2019043-1 · issued Mar 27, 2019 · closed Mar 31, 2023Closed
- Ensures that the Authority complies with the subrecipient monitoring requirements.DOT OIG SA2019069-1 · issued Sep 10, 2019 · closed Mar 31, 2023Closed
- KPMG recommends that FTA management design and implement policies and procedures that establish a formal process to assess applicable third-party SOC reports that includes reviewing the…DOT OIG QC2021015-6 · issued Jan 27, 2021 · closed Mar 30, 2023Closed
- KPMG recommends that FTA management design and implement policies and procedures that establish a formal process to assess applicable third-party SOC reports that includes implementing the…DOT OIG QC2021015-7 · issued Jan 27, 2021 · closed Mar 30, 2023Closed
- Conduct, document, and communicate the results of its annual incident response and data breach plan testing for financial management systems before authorization to operate (ATO); to…DOT OIG IT2022005-10 · issued Oct 20, 2021 · closed Jan 13, 2023Closed
- Develop and implement a plan that ensures continuity of federal workforce and contractual resources to fulfill contingency responsibilities for its financial management systems (FMS and…DOT OIG IT2022005-9 · issued Oct 20, 2021 · closed Jan 13, 2023Closed
- Require the Hurricane Sandy Recovery grantees to apply their insurance proceeds in accordance with the timeframe established in the revised ERP guidance and in support of the policy…DOT OIG ST2020005-5 · issued Oct 30, 2019 · closed Jan 11, 2023Closed
- Implement secure configuration settings for its financial management systems (FMS and ECHO-Web) databases in accordance with Federal and DOT policies.DOT OIG IT2022005-7 · issued Oct 20, 2021 · closed Dec 14, 2022Closed
- Sensitive information redactedDOT OIG IT2022005-8 · issued Oct 20, 2021 · closed Dec 5, 2022Closed
- Recovers $9,189 from the Agency, if applicable. ÂDOT OIG SA2017058-2 · issued Jun 6, 2017 · closed Sep 30, 2022Closed
- Ensures that the City and County complies with the reporting requirements.DOT OIG SA2018080-3 · issued Sep 10, 2018 · closed Sep 30, 2022Closed
- Update the security assessment documents for its financial management systems (FMS, ECHO-Web, and TrAMS) to properly reflect the results of all security controls (e.g., common, hybrid, and…DOT OIG IT2022005-3 · issued Oct 20, 2021 · closed Sep 23, 2022Closed
- Obtain and assess all up-to-date security authorization documents associated with its financial management systems (FMS, ECHO-Web, and TrAMS) inherited controls (e.g. common, hybrid) to…DOT OIG IT2022005-4 · issued Oct 20, 2021 · closed Sep 23, 2022Closed
- Require the FTA Information System Security Manager (ISSM)/ Privacy Officer to adhere to its Incident and Data Breach Response Plan to report recipient cybersecurity incidents involving…DOT OIG IT2022005-12 · issued Oct 20, 2021 · closed Aug 19, 2022Closed
- Perform an assessment of its financial management systems (FMS, ECHO-Web, and TrAMS) security controls that at a minimum reflect the correct security control types and update each system’s…DOT OIG IT2022005-2 · issued Oct 20, 2021 · closed Aug 18, 2022Closed
- Ensures that the City complies with the subrecipient monitoring requirements.DOT OIG SA2019035-1 · issued Mar 26, 2019 · closed Jun 7, 2022Closed
- Ensures that the City complies with the allowable costs/cost principles requirements.DOT OIG SA2019038-1 · issued Mar 26, 2019 · closed Jun 7, 2022Closed
- Recovers $1,656 from the City, if applicable.DOT OIG SA2019038-2 · issued Mar 26, 2019 · closed Jun 7, 2022Closed
- Establish, document, and implement a security incident reporting process and procedures for its recipients to report incidents that affect their login credentials.DOT OIG IT2022005-11 · issued Oct 20, 2021 · closed May 18, 2022Closed
- Ensures that the Agency complies with the procurement and suspension and debarment requirements.DOT OIG SA2018067-1 · issued Aug 15, 2018 · closed Mar 18, 2022Closed
- Recover $83,547 from the City, if applicable.DOT OIG SA2019026-2 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Recover $30,335 from the City, if applicable.DOT OIG SA2019026-4 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Recover $13,465 from the City, if applicable.DOT OIG SA2019026-6 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Recover $41,733 from the City, if applicable.DOT OIG SA2019027-2 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Recover $107,181 from the City, if applicable.DOT OIG SA2019027-4 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Recover $8,067 from the City, if applicable.DOT OIG SA2019027-6 · issued Mar 25, 2019 · closed Mar 18, 2022Closed
- Ensures that the Authority complies with the subrecipient monitoring requirements.DOT OIG SA2019079-1 · issued Sep 18, 2019 · closed Mar 14, 2022Closed
- KPMG recommends that FTA management perform a documentedrisk assessment and develop a tailored grant accrual methodology for each newgrant accrual category in which the expected costs…DOT OIG QC2021008-6 · issued Jan 27, 2021 · closed Mar 7, 2022Closed
- KPMG recommendeds that FTA management establish a documented review process to clearly demonstrate the historical disbursement days for all grant accrual categories have been reviewed…DOT OIG QC2021008-7 · issued Jan 27, 2021 · closed Mar 7, 2022Closed
- Select and implement security control-process isolation to protect its financial management systems (FMS and ECHO-Web) against risk.DOT OIG IT2022005-1 · issued Oct 20, 2021 · closed Feb 1, 2022Closed
- Sensitive information redactedDOT OIG IT2022005-6 · issued Oct 20, 2021 · closed Jan 31, 2022Closed
- Ensures that the Authority complies with the procurement and suspension and debarment requirements.DOT OIG SA2018045-1 · issued Apr 30, 2018 · closed Jan 13, 2022Closed
- Ensures that the Authority complies with the subrecipient monitoring requirements.DOT OIG SA2018045-2 · issued Apr 30, 2018 · closed Jan 13, 2022Closed
- Recovers $214,494 from the Agency, if applicable.DOT OIG SA2018067-2 · issued Aug 15, 2018 · closed Jan 11, 2022Closed
- Recovers $2,780,059 from the City, if applicable.DOT OIG SA2018083-2 · issued Sep 10, 2018 · closed Jan 11, 2022Closed
- Complete the planned update to FTA’s Assistance Listings internal guidance to include procedures to ensure the Agency complies with the Office of Management and Budget assistance listing…DOT OIG ST2021032-2 · issued Jul 21, 2021 · closed Nov 23, 2021Closed
- Assess the necessary data to affirm that Hurricane Sandy recovery grantees carried flood insurance that complied with the Flood Disaster Protection Act (FDPA). For any Hurricane Sandy…DOT OIG ST2020005-2 · issued Oct 30, 2019 · closed Oct 29, 2021Closed
- KPMG recommends that FTA management revise the existing configuration management plans for the grant financial management application and the clearing house system to include procedures…DOT OIG QC2021015-1 · issued Jan 27, 2021 · closed Sep 30, 2021Closed
- KPMG recommends that FTA management reconfigure the grants management application to automatically remove roles that are not recertified annually.DOT OIG QC2021015-2 · issued Jan 27, 2021 · closed Sep 30, 2021Closed
- KPMG recommends that FTA management reconfigure the application that supports the grants management system to automatically disable accounts after 60 days of inactivity.DOT OIG QC2021015-3 · issued Jan 27, 2021 · closed Sep 30, 2021Closed
- KPMG recommends that FTA management update the grants management system platform's system security plan to reflect the configuration considerations in place.DOT OIG QC2021015-4 · issued Jan 27, 2021 · closed Sep 30, 2021Closed
- Ensures that the Authority complies with subrecipient monitoring requirements.DOT OIG SA2018069-1 · issued Aug 15, 2018 · closed Sep 29, 2021Closed
- Ensures that the Authority complies with the subrecipient monitoring requirements.DOT OIG SA2019034-1 · issued Mar 27, 2019 · closed Sep 29, 2021Closed
- KPMG recommends that FTA management ensure that new users are properly authorized by all required parties prior to the administration of access to FTA systems.DOT OIG QC2021015-5 · issued Jan 27, 2021 · closed Sep 27, 2021Closed
- Provide guidance or training on Master Agreement notification requirements for grantees and integrity monitors, such as defining what is meant by providing “prompt” notification.DOT OIG ZA2019064-5 · issued Sep 9, 2019 · closed Aug 18, 2021Closed
- Require MTA to apply the full amount of its transit-related insurance proceeds to eligible transit projects. Implementation of this recommendation could put up to $180.7 million in funds…DOT OIG ST2020005-6 · issued Oct 30, 2019 · closed Jul 29, 2021Closed
- Develop and implement guidance for determining threats and impediments to independence. The guidance should address criteria for independence, including the use of internal grantee staff…DOT OIG ZA2019064-2 · issued Sep 9, 2019 · closed Jun 22, 2021Closed
- Revise the ERP Toolkit checklist to include a step for FTA Regional staff to crosscheck against the approved insurance allocation plan when reviewing Hurricane Sandy grant applications and…DOT OIG ST2020005-8 · issued Oct 30, 2019 · closed May 27, 2021Closed
- KPMG recommends that FTA management design and implement a process to ensure that a complete population of received FFRs are considered in the retrospective review.DOT OIG QC2020025-1 · issued Apr 8, 2020 · closed May 4, 2021Closed
- KPMG recommends that FTA management document the revised FFR submission policy in their grant methodology to consider the potential impact on the retrospective review process.DOT OIG QC2020025-2 · issued Apr 8, 2020 · closed May 4, 2021Closed
- Ensures that the City complies with allowable costs/cost principles Requirements.DOT OIG SA2017052-1 · issued Jun 6, 2017 · closed Apr 14, 2021Closed
- Develop and implement procedures for consistently reviewing,approving and periodically updating grantee integrity monitor plans.DOT OIG ZA2019064-1 · issued Sep 9, 2019 · closed Feb 16, 2021Closed
- Develop and implement procedures requiring all participants in grantee integrity monitoring activities to promptly notify the grantee and FTA when they have knowledge of current or…DOT OIG ZA2019064-3 · issued Sep 9, 2019 · closed Feb 16, 2021Closed
- Develop and implement procedures for periodically assessingwhether integrity monitors are meeting plan expectations, and for takingappropriate corrective actions when integrity monitors…DOT OIG ZA2019064-6 · issued Sep 9, 2019 · closed Feb 16, 2021Closed
- Inform integrity monitors about best practices for targetingnew risk areas, such as procedures for contractor responsibilitydeterminations, and updating plans accordingly.DOT OIG ZA2019064-7 · issued Sep 9, 2019 · closed Feb 16, 2021Closed
- Develop and implement procedures for grantee oversight of integrity monitors that include a review of quarterly reports that, at a minimum contain information about integrity monitor…DOT OIG ZA2019064-8 · issued Sep 9, 2019 · closed Feb 16, 2021Closed
- Revise FTA’s Emergency Relief Program (ERP) guidance to include a timeframe within which grantees must apply insurance proceeds to support the policy described in its ERP Final Rule.DOT OIG ST2020005-4 · issued Oct 30, 2019 · closed Jan 15, 2021Closed
- Develop procedures to track grantee allocation plan implementation for expenditures solely funded with insurance proceeds.DOT OIG ST2020005-7 · issued Oct 30, 2019 · closed Jan 15, 2021Closed
- Ensures that the City and County complies with the activities allowed or unallowed and allowable costs/cost principles requirements.DOT OIG SA2018080-1 · issued Sep 10, 2018 · closed Oct 27, 2020Closed
- Ensures that the City and County complies with the reporting requirements.DOT OIG SA2019058-1 · issued Jul 31, 2019 · closed Oct 27, 2020Closed
- Reduce permanently NYC DOT's Hurricane Sandy total damage assessment by $2.125 million to remove the ineligible expenses.DOT OIG ST2020005-1 · issued Oct 30, 2019 · closed Sep 28, 2020Closed
- Ensure the Authority implement security controls and devices to ensure that equipment is properly safeguarded. This finding affects ARRA fundsDOT OIG SA2011069-3 · issued Mar 23, 2011 · closed Sep 24, 2020Closed
- Ensures that the Authority complies with the cash management requirements.DOT OIG SA2018078-1 · issued Sep 10, 2018 · closed Jul 30, 2020Closed
- Ensures that the Authority complies with the reporting requirements.DOT OIG SA2019028-2 · issued Mar 25, 2019 · closed Apr 7, 2020Closed
- Ensures that the University complies with the allowable costs/cost principles requirements.DOT OIG SA2018087-3 · issued Sep 11, 2018 · closed Mar 31, 2020Closed
- Ensure that the Metro Regional Transit Authority complies with the special tests and provisions requirements.DOT OIG SA2019032-1 · issued Mar 26, 2019 · closed Mar 25, 2020Closed
- Ensures that the District complies with the activities allowed or unallowed requirements.DOT OIG SA2019039-1 · issued Mar 26, 2019 · closed Mar 25, 2020Closed
- Ensure that the City comply with the Allowable Costs/Cost Principles requirement.DOT OIG SA2019026-1 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensure that the City comply with the Allowable Costs/Cost Principles requirements.DOT OIG SA2019026-3 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensure that the City comply with cash management requirements.DOT OIG SA2019026-5 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensure that the City complies with the activities allowed or unallowed requirements.DOT OIG SA2019027-1 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensure that the City complies with the allowable costs/cost principles requirements.DOT OIG SA2019027-3 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensure that the City complies with the matching, level of effort, earmarking requirements.DOT OIG SA2019027-5 · issued Mar 25, 2019 · closed Mar 24, 2020Closed
- Ensures that the Municipality complies with the activities allowed or unallowed requirements.DOT OIG SA2019061-2 · issued Jul 31, 2019 · closed Feb 12, 2020Closed
- Recovers $151 from the Municipality, if applicable.DOT OIG SA2019061-3 · issued Jul 31, 2019 · closed Feb 12, 2020Closed
- Ensures that the Municipality complies with the equipment and real property management requirements.DOT OIG SA2019061-4 · issued Jul 31, 2019 · closed Feb 12, 2020Closed
- Recovers $64,220 from the Municipality, if applicable.DOT OIG SA2019061-5 · issued Jul 31, 2019 · closed Feb 12, 2020Closed
- Recover the estimated $1.1 million that represents FTA's share of the settlement funds paid to PANYNJ-OIG.DOT OIG ZA2019064-4 · issued Sep 9, 2019 · closed Oct 22, 2019Closed
- Ensures that the State complies with the subrecipient monitoring requirements.DOT OIG SA2018081-1 · issued Sep 10, 2018 · closed Sep 26, 2019Closed
- Recovers $106,181 from the State, if applicable.DOT OIG SA2018081-2 · issued Sep 10, 2018 · closed Sep 26, 2019Closed
- Ensure the Authority complies with the Reporting Requirements.DOT OIG SA2016105-1 · issued Sep 19, 2016 · closed Sep 24, 2019Closed
- Ensure the Authority complies with the Cash Management Requirements.DOT OIG SA2016105-2 · issued Sep 19, 2016 · closed Sep 24, 2019Closed
- Ensure the Authority complies with the Special Tests and Provisions Requirements.DOT OIG SA2016105-3 · issued Sep 19, 2016 · closed Sep 24, 2019Closed
- Ensures that the City complies with the subrecipient monitoring requirements.DOT OIG SA2018083-1 · issued Sep 10, 2018 · closed Sep 3, 2019Closed
- Ensure that the Authority complies with the equipment and real property management requirements.DOT OIG SA2018035-1 · issued Mar 19, 2018 · closed Aug 27, 2019Closed
- Ensures that the Council complies with the special tests and provisions requirements.DOT OIG SA2018075-1 · issued Aug 22, 2018 · closed Aug 27, 2019Closed
- Recovers $21,265 from the City, if applicable.DOT OIG SA2018042-2 · issued Apr 30, 2018 · closed Aug 22, 2019Closed
- Ensure the Authority update and modify the security controls at the bus divisions to prevent or detect unauthorized entry.DOT OIG QC2007057-1 · issued Jul 18, 2007 · closed Aug 15, 2019Closed
- Recovers $37,543 from the City, if applicable.DOT OIG SA2018042-4 · issued Apr 30, 2018 · closed Aug 14, 2019Closed
- Ensures that the Authority complies with the subrecipient monitoring requirements.DOT OIG SA2018089-1 · issued Sep 11, 2018 · closed Aug 14, 2019Closed
- Determine their portion of the $29,116 in Questioned Costs and recovers from the Authority, if applicable.DOT OIG SA2017053-2 · issued Jun 6, 2017 · closed Jul 31, 2019Closed
- Ensures that the City complies with the allowable cost/cost principles requirements.DOT OIG SA2018042-3 · issued Apr 30, 2018 · closed Jul 31, 2019Closed
- Ensures that the District complies with the procurement and suspension and debarment requirements.DOT OIG SA2018100-1 · issued Sep 12, 2018 · closed Jul 31, 2019Closed
- Ensures that the Authority complies with the cash management requirements.DOT OIG SA2019033-1 · issued Mar 26, 2019 · closed Jul 31, 2019Closed
- Recovers $221,551 from the District, if applicable.DOT OIG SA2019039-2 · issued Mar 26, 2019 · closed Jul 31, 2019Closed
- Ensure that the Authority complies with the special tests and provisions requirements.DOT OIG SA2018035-2 · issued Mar 19, 2018 · closed Jul 30, 2019Closed
- Ensures that the DART complies with the allowable costs/cost principles requirements.DOT OIG SA2018048-1 · issued Apr 30, 2018 · closed Jul 30, 2019Closed
- We recommend FTA recovers $122,558 from the DART, if applicale.DOT OIG SA2018048-2 · issued Apr 30, 2018 · closed Jul 30, 2019Closed
- Ensures that the State complies with the reporting requirements.DOT OIG SA2018079-7 · issued Sep 10, 2018 · closed Jul 30, 2019Closed
- Ensures that the Authority complies with the reporting requirements.DOT OIG SA2018090-1 · issued Sep 11, 2018 · closed Jul 30, 2019Closed
- Ensures that the City complies with procurement and suspension and debarment requirements.DOT OIG SA2019040-1 · issued Mar 26, 2019 · closed Jul 29, 2019Closed
- Recovers $81,888 from the City, if applicable.DOT OIG SA2019040-2 · issued Mar 26, 2019 · closed Jul 29, 2019Closed
- Ensure that the Authority complies with the procurement and suspension and debarment requirements.DOT OIG SA2018034-1 · issued Mar 19, 2018 · closed Jul 18, 2019Closed
- Ensures that the City complies with the allowable cost/cost principles requirements.DOT OIG SA2018042-1 · issued Apr 30, 2018 · closed Jul 18, 2019Closed
- Recovers $2,787 from the Authority, if applicable.DOT OIG SA2018093-2 · issued Sep 11, 2018 · closed Jul 18, 2019Closed
- Ensures that the DART complies with the cash management requirements.DOT OIG SA2018048-3 · issued Apr 30, 2018 · closed Jul 17, 2019Closed