Review and take corrective action to address the approximately $95.4 million in questioned costs based on recipients incurring new project costs…

ClosedThe publisher's status, as reported by DOT Office of Inspector General in the file read .

The recommendation, in the publisher's words

Review and take corrective action to address the approximately $95.4 million in questioned costs based on recipients incurring new project costs during lapses in the grants’ periods of performance.
Responsible agency
Federal Transit Administration
Issued
November 19, 2025
Report
FTA’s Oversight Is Insufficient To Verify Timely and Proper Spending of Hurricane Sandy Funds (FI2026001) · find it at DOT OIG
Closed
July 7, 2026 (publisher's date)
Questioned costs
$95,425,874 (the publisher's figure; not realised savings)

“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.

Dated history

  1. Issued by DOT OIG. (publisher's date)
  2. Closed, with status “Closed”. (publisher's date)
  3. First recorded by AuditLine. (start of AuditLine's own history for this record)

Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.

Other recommendations from this report

3 more, of which 0 are open in the publisher's file.

Source

Open this report in DOT OIG's tracker This publisher's records (CSV)