DOT OIG recommendation ST2015046-3
Improve FTA's risk assessment process for future grantee and project risk assessments by: a.) establishing criteria for assigning low, medium, and…
The recommendation, in the publisher's words
Improve FTA's risk assessment process for future grantee and project risk assessments by: a.) establishing criteria for assigning low, medium, and high risks and b.) requiring documentation that allows others to understand how these criteria inform specific risk assessment ratings and, if applicable, the reason(s) and decision-making for different risk levels assigned to grantee risk assessments and the grantees' project risk assessments.
- Responsible agency
- Federal Transit Administration
- Issued
- June 12, 2015
- Report
- FTA Has Not Fully Implemented Key Internal Controls for Hurricane Sandy Oversight and Future Emergency Relief Efforts (ST2015046) · find it at DOT OIG
- Closed
- May 24, 2016 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
4 more, of which 0 are open in the publisher's file.
- Implement enhanced review processes for ERP grant applications and grant award approvals that are aligned with the ERP Toolkit's checklists and require documentation in FTA's grant…DOT OIG ST2015046-1 · issued Jun 12, 2015 · closed May 24, 2016Closed
- Enhance internal control processes for future force account funding by establishing clear funding criteria for future emergency relief efforts, which include the specific types of…DOT OIG ST2015046-2 · issued Jun 12, 2015 · closed Feb 4, 2016Closed
- Develop and implement enhanced controls to ensure that monthly ERP FFR and MPR review processes, as outlined in the ERP Toolkit, are fully implemented by regional office personnel and…DOT OIG ST2015046-4 · issued Jun 12, 2015 · closed Feb 4, 2016Closed
- Formalize FTA's process for coordination with FEMA to avoid duplicative payments in providing emergency and disaster-related assistance.DOT OIG ST2015046-5 · issued Jun 12, 2015 · closed Oct 6, 2016Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.