DOT OIG recommendation ST2020035-2
Identify and notify Divisions about sources of information that can inform the project risk-assessment process, such as the quarterly reports…
The recommendation, in the publisher's words
Identify and notify Divisions about sources of information that can inform the project risk-assessment process, such as the quarterly reports required by the grant agreement for the Florida International University project.
- Responsible agency
- Federal Highway Administration
- Issued
- May 19, 2020
- Report
- Gaps in FHWA’s Guidance and the Florida Division’s Process for Risk-Based Project Involvement May Limit Their Effectiveness (ST2020035) · find it at DOT OIG
- Closed
- February 22, 2021 (publisher's date)
“Open” and “closed” are the publisher's words. AuditLine repeats them with the date it read them. It does not check whether a recommendation was carried out, and a closed recommendation is not proof that a problem was fixed.
Dated history
- Issued by DOT OIG. (publisher's date)
- Closed, with status “Closed”. (publisher's date)
- First recorded by AuditLine. (start of AuditLine's own history for this record)
Dates marked "publisher's date" come from the publisher's file. AuditLine's own observations begin November 10, 2026 and are added each time the publisher's file changes.
Other recommendations from this report
7 more, of which 0 are open in the publisher's file.
- Update and implement FHWA's guidance for risk-based project involvement to clarify the requirements for its project risk-assessment process, including expectations for conducting and…DOT OIG ST2020035-1 · issued May 19, 2020 · closed Feb 22, 2021Closed
- Update and issue a procedure within the Florida Division for conducting and documenting complete project risk assessments in accordance with FHWA's national guidance.DOT OIG ST2020035-3 · issued May 19, 2020 · closed Dec 15, 2021Closed
- Update and implement FHWA's guidance for risk-based project involvement to clarify how the link between elevated risks and associated oversight activities, changes to oversight actions,…DOT OIG ST2020035-4 · issued May 19, 2020 · closed Feb 22, 2021Closed
- Develop and implement guidance for documenting, in risk-based project oversight plans and associated materials, the scope of FHWA's risk-based involvement, such as through the use of…DOT OIG ST2020035-5 · issued May 19, 2020 · closed Feb 22, 2021Closed
- Develop and implement guidance that establishes criteria for the content of risk-based project oversight plans to maintain consistency and avoid creating multiple redundant plans. Include…DOT OIG ST2020035-6 · issued May 19, 2020 · closed Feb 22, 2021Closed
- Update and issue a procedure within the Florida Division for documenting complete risk-based project oversight plans in accordance with FHWA's national guidance.DOT OIG ST2020035-7 · issued May 19, 2020 · closed Dec 15, 2021Closed
- Develop and implement a process to routinely monitor the implementation and evaluate the effectiveness of FHWA’s risk-based project involvement.DOT OIG ST2020035-8 · issued May 19, 2020 · closed May 9, 2022Closed
Source
Open this report in DOT OIG's tracker This publisher's records (CSV)
Official export: https://www.oig.dot.gov/recommendation-dashboard/export?page&_format=csv. File read , 3,436 rows,
SHA-256 6406a142cdf501ec…. DOT OIG's status and dollar figures are the publisher's own claims. Recommendations it marks sensitive are listed without their text.